The European Council announced on 18 November 2026 that a preliminary agreement had been reached with the European Parliament. The document is aimed at speeding up the issuance of permits for renewable energy projects, electricity grids and energy storage facilities.
The goal is to reduce the multi-year delays that are holding back the sector's development. EU countries have invested substantial funds in cheap renewable energy, but grid modernisation is lagging behind.
This leads to curtailment of wind and solar generation, capacity losses and rising prices. The new rules will allow member states to treat such projects as having an "overriding public interest" and thereby speed up their implementation.
The agreement is part of a package of measures on European grids presented at the end of 2025 year. It is intended to modernise and expand the bloc's energy infrastructure as part of the transition to climate neutrality.
The permits directive amends the renewable energy directive, the electricity market directive and the gas market directive. The document now requires formal approval by both sides.
After that, member states will have a year and a half to transpose the rules into national legislation. Will this actually be able to speed up Europe's transition to clean energy?
One thing is clear for now: without solving the grid problem, investment in renewable sources risks remaining not fully realised.